boundary="_000_PR2PR03MB51938AACC07FF2012C42011DB3350PR2PR03MB5193eurp_" ****************************************************************************** dorisreport 28-Sep-2020 13:10:49 Message No 5135 ****************************************************************************** Author: Katsigianni Georgia Subject: CRYOSAT - ARC543 - DORIS data and final orbit delivery --_000_PR2PR03MB51938AACC07FF2012C42011DB3350PR2PR03MB5193eurp_ Dear colleagues, Arc : 543 From August 30th, 2020 to September 5th, 2020 (period used for processing: = from August 29th, 2020 to September 6th, 2020) Missing data : none. Maneuver : none. Incident : none. Events : none. Doris data and final orbit were delivered today. These data will be automatically delivered to the IDS Data Centers within 2= 4 hours. Best regards, Gina --_000_PR2PR03MB51938AACC07FF2012C42011DB3350PR2PR03MB5193eurp_

Dear colleagues,

 

Arc  : 543

From August 30th, 2020 to September 5th, 2020 (period used for processing= : from August 29th, 2020 to September 6th, 2020)

 

Missing data : none.

Maneuver :     none.

Incident :     none.

Events   :     none.

 

Doris data and final orbit were delivered today.

These data will be automatically delivered to the IDS Data Centers within= 24 hours.

 

Best regards,

Gina

--_000_PR2PR03MB51938AACC07FF2012C42011DB3350PR2PR03MB5193eurp_-- Please do not reply directly to this message, but send comments and suggestions to IDS.central.bureau@cls.fr