boundary="_000_60D7494397CAD54086123F87123B50B51A65C56ATWMBXP04cnesnet_" ****************************************************************************** dorisreport 05-Feb-2018 10:00:52 Message No 4468 ****************************************************************************** Author: "Ait Lakbir Hanane (CS SI)" Subject: CRYOSAT - ARC405 - DORIS data and final orbit delivery --_000_60D7494397CAD54086123F87123B50B51A65C56ATWMBXP04cnesnet_ Dear colleagues, Arc : 405 From January 7th, 2018 to January 13th, 2018 (period used for processing: f= rom January 6th, 2018 to January 14th, 2018) Missing data : none. Maneuver : none. Incident : none. Events : none. Doris data and final orbit were delivered today. These data will be automatically delivered to the IDS Data Centers within 2= 4 hours. Best regards, Hanane --_000_60D7494397CAD54086123F87123B50B51A65C56ATWMBXP04cnesnet_

Dear colleagues,

 

Arc  : 405

From January 7th, 2018 to January 13th, 2018 (period used = for processing: from January 6th, 2018 to January 14th, 2018)

Missing data : none.

Maneuver :     none.

Incident :     none.

Events   :     none.<= span lang=3D"EN-US">

 

Doris data and final orbit were delivered today.

These data will be automatically delivered to the IDS Data= Centers within 24 hours.

 

Best regards,

Hanane

--_000_60D7494397CAD54086123F87123B50B51A65C56ATWMBXP04cnesnet_-- Please do not reply directly to this message, but send comments and suggestions to IDS.central.bureau@cls.fr