boundary="_000_60D7494397CAD54086123F87123B50B513EAD262TWMBXP04cnesnet_" ****************************************************************************** dorisreport 07-Mar-2016 13:49:45 Message No 4030 ****************************************************************************** Author: "Ait Lakbir Hanane (CS SI)" Subject: CRYOSAT - ARC305 - DORIS data and final orbit delivery --_000_60D7494397CAD54086123F87123B50B513EAD262TWMBXP04cnesnet_ Dear colleagues, Arc : 305 from February 7th, 2016 to February 13th, 2016 (period used for processing:= from February 6th, 2016 to February 14th, 2016) Missing data : none. Maneuver : none Incident : none. Events : none. Doris data and final orbit were delivered today. These data will be automatically delivered to the IDS Data Centers within 2= 4 hours. Best regards, Hanane --_000_60D7494397CAD54086123F87123B50B513EAD262TWMBXP04cnesnet_

Dear colleagues,

 

Arc  : 305

from February 7th, 2016 to February 13th, 2016 (period use= d for processing: from February 6th, 2016 to February 14th, 2016)

 

Missing data : none.

Maneuver :     none

Incident :     none.

Events   :     none.<= span lang=3D"EN-US">

 

Doris data and final orbit were delivered today.

These data will be automatically delivered to the IDS Data= Centers within 24 hours.

 

Best regards,

Hanane

 

--_000_60D7494397CAD54086123F87123B50B513EAD262TWMBXP04cnesnet_-- Please do not reply directly to this message, but send comments and suggestions to IDS.central.bureau@cls.fr