boundary="_000_4A209E6EBA46214D892C9CB9FDE8898784D00D02TWMBXP03cnesnet_" ****************************************************************************** dorisreport 12-Jan-2015 14:12:28 Message No 3769 ****************************************************************************** Author: Moyard John Subject: Jason2 CY237 DORIS data and final orbit delivery --_000_4A209E6EBA46214D892C9CB9FDE8898784D00D02TWMBXP03cnesnet_ Dear colleagues, Satellite : Jason2 Cycle : 237 from December, 8, 2014 to December, 18, 2014 Missing data : none. Manoeuvre : In-plane maneuver on the 10th of December, 2014, 5h01. Incident : none. Events : none. DORIS data and final POE orbit were delivered today. These data will be automatically delivered to the IDS Data Centers within 2= 4 hours. Best Regards, John --_000_4A209E6EBA46214D892C9CB9FDE8898784D00D02TWMBXP03cnesnet_
Dear colleagues,
 
Satellite : Jason2
Cycle : 237
from December, 8, 2014 to December, 18, 2014
 
Missing data : none.
Manoeuvre :    In-plane maneuver on the 10th of Decembe= r, 2014, 5h01.
Incident :     none.
Events   :     none
 
DORIS data and final POE orbit were delivered today.
These data will be automatically delivered to the IDS Data Centers wit= hin 24 hours.
 
 
Best Regards,
John
 
 
--_000_4A209E6EBA46214D892C9CB9FDE8898784D00D02TWMBXP03cnesnet_-- Please do not reply directly to this message, but send comments and suggestions to IDS.central.bureau@cls.fr